BESScompliance logoBESScompliance
Grid Code/Denmark
DKTSO: Energinet

Denmark — Grid Code for Energy Storage

Energinet's grid code framework for battery energy storage systems connected to the Danish electricity supply system. The primary specification is Technical Regulation 3.3.1 (Revision 6), effective from 1 May 2025. Denmark operates in two synchronous areas: DK1 (Continental Europe) and DK2 (Nordic).

93
Pages
20
Parts
DK1 / DK2
Synchronous areas
1.5.2025
Effective date

What makes TR 3.3.1 different

Two synchronous areas (DK1 / DK2)

Denmark spans Continental Europe (DK1, West) and Nordic (DK2, East). Frequency control settings differ: LFSM-O breakpoint is 50.20 Hz in DK1 vs 50.50 Hz in DK2. FSM bands also differ between areas.

Dedicated storage regulation

TR 3.3.1 is a standalone regulation written specifically for energy storage facilities — not a repurposed generation code. It covers both synchronous and non-synchronous storage, plus V2G.

V2G explicitly in scope

Vehicle-to-Grid (V2G) bi-directional charging stations are explicitly included. The regulation specifies that either the charging station or transport owner must comply, depending on where conversion occurs.

Lower type thresholds

Type boundaries are lower than many EU countries: Type A up to 125 kW, Type B 125 kW – 3 MW, Type C 3 – 25 MW, Type D ≥ 25 MW or ≥ 110 kV. Most utility-scale BESS fall under Type C or D.

Type categories (TR 3.3.1 Section 2)

Type A
Up to 125 kW
Type B
125 kW – 3 MW
Type C
3 – 25 MW
Type D
≥ 25 MW or ≥ 110 kV

Most utility-scale BESS projects in Denmark fall under Type C or D. Type D also requires island mode capability and simulation models.

Main specification

Technical Regulation 3.3.1 — Requirements for Energy Storage Facilities (Revision 6)

93-page regulation covering 20 parts: scope and definitions, requirements per type (A–D), synchronous and non-synchronous storage, transmission-connected facilities, compliance testing, simulation, and grid connection procedure.

Frequency controlFRTReactive powerProtectionPower qualityV2G
PDF

View all TR 3.3.1 requirements

Full requirement breakdown by functional category — operating ranges, FRT, frequency control, reactive power, protection, compliance testing.

Key technical parameters (Type C/D)

ParameterDK1 (Continental)DK2 (Nordic)
Continuous frequency49.0–51.0 Hz49.0–51.0 Hz
Extended frequency (30 min)47.5–49.0 / 51.0–51.5 Hz47.5–49.0 / 51.0–51.5 Hz
LFSM-O breakpoint50.20 Hz, 5% droop50.50 Hz, 4% droop
LFSM-U breakpoint49.80 Hz, 5% droop49.50 Hz, 4% droop
FSM band49.80–50.20 Hz49.50–50.50 Hz
RoCoF withstand± 2 Hz/s± 2 Hz/s
Phase jump withstand20°20°
OV-FRT1.20 Uc for 5s, 1.15 Uc for 60s1.20 Uc for 5s, 1.15 Uc for 60s
Voltage control (90%)Within 1 secondWithin 1 second
System protection levels5 levels: 70/50/40/10/0%5 levels: 70/50/40/10/0%

Grid connection process

The compliance process for connecting a BESS to the Danish grid follows TR 3.3.1 Part 19. The relevant system operator (DSO or Energinet for transmission) manages the process.

1

Application

Before connection agreement

Submit facility information to the relevant system operator (DSO or Energinet): rated power (Pnl/Pno), usable energy storage capacity, storage medium details, and CE declaration of conformity.

2

Grid connection agreement

Before construction

Agree on connection point, rated power, reactive power requirements, protection settings, and signal exchange. Type D facilities require Energinet authorisation for automatic connection.

3

Simulation models (Type D)

Before commissioning

Type D facility owners must prepare and submit simulation models equivalent to those required for generation facilities under NC RfG and NC DC.

4

Compliance testing

Before commercial operation

Demonstrate compliance through commissioning tests or simulations as agreed with the relevant system operator. Tests cover frequency response, reactive power, FRT, protection, and power quality.

5

Interim Operating Notification (ION)

After testing

The relevant system operator issues an ION once compliance is demonstrated. The facility may operate commercially while any remaining compliance items are resolved.

6

Final compliance

Ongoing

Facility must maintain compliance throughout its operational life. The DSO or Energinet may require changes to protection settings after commissioning.

Documents

Energinet publishes technical regulations and supplementary documents for grid-connected energy storage facilities.

Key stakeholders

Energinet (TSO)

Transmission system operator for Denmark. Sets technical regulations, manages transmission-connected facilities, and authorises Type D automatic connection. Operates both DK1 and DK2.

Electricity regulations

DSO (Distribution System Operator)

The relevant system operator for distribution-connected facilities. Coordinates protection settings, approves grid connection, and receives compliance test results. First point of contact for most BESS projects.

Facility Owner

Legally responsible for ensuring the energy storage facility meets all requirements. Must bear all compliance costs, provide facility information, and maintain compliance throughout operation.