BESScompliance logoBESScompliance
Grid Code/Finland
FITSO: Fingrid

Finland — Grid Code for Energy Storage

Fingrid's grid code framework for battery energy storage systems connected to the Finnish transmission and distribution network. The primary specification is SJV2024, supported by complementary documents covering modelling, cybersecurity, and stability studies.

161
Requirements
16
Commissioning tests
15
Sections
15.1.2025
Effective date

What makes SJV2024 different

Grid-forming is mandatory

All new BESS must operate in grid-forming mode at all times — not configurable, not optional. Finland is one of the first countries in Europe to require this.

Zero-voltage FRT for Type D

Type D systems must ride through 0.00 pu for 200 ms. Type B/C ride through 0.05 pu for 150 ms. Among the most demanding FRT profiles in Europe.

RoCoF relays banned (Type C/D)

Rate-of-change-of-frequency protection relays are explicitly prohibited for Type C and D. Only allowed for Type A/B with ≥ 4 Hz/s threshold.

16 commissioning tests

Type C/D systems must pass 16 on-site tests with ≥ 90% of converters operational — covering LFSM, FSM, voltage control, FRT, island detection, and more. One of the most extensive test programs in Europe.

Type categories (SJV2024 Table 3.1)

Type A
0.8 kW – 1 MW
Type B
1 – 10 MW
Type C
10 – 30 MW
Type D
≥ 30 MW or ≥ 110 kV

Most utility-scale BESS projects in Finland fall under Type C or D. SJV2024 focuses on these categories.

Main specification

SJV2024 — Grid Code Specifications for Grid Energy Storage Systems

161 requirements across 15 categories: operating ranges, FRT, grid-forming, active/reactive power control, protection, SCADA interfaces, commissioning tests, and simulation models.

Live

Grid connection process

The compliance process for connecting a BESS to the Finnish grid follows a staged approach. Each stage shows the documents you need at that point.

1

Stage 0 — Preliminary planning

Before connection agreement

Complete the Stage 0 questionnaire. Provide preliminary technical data, site layout, and planned capacity to Fingrid and the relevant network operator (RNO).

2

Stage 1 — Connection agreement

Before connection agreement

Deliver detailed technical data, reactive power capacity calculation, and preliminary simulation models (PSS/E + PSCAD).

3

Dynamic studies

6 months before first power supply

Prepare and submit dynamic study results and simulation models to RNO and Fingrid. Covers voltage disturbance, constant voltage control, vector shift, island operation, and impedance scan.

4

Test plan

2 months before commissioning

Submit test plan, preliminary instructions, and practical arrangements for commissioning tests.

5

Commissioning

Before commercial operation

Execute 16 commissioning tests (Type C/D) with ≥ 90% of converters operational. Tests cover LFSM, FSM, voltage control, reactive power, FRT, island mode, and more.

6

Model verification

After commissioning

Compare simulation results against commissioning test data. Deliver verification report and update models if needed.

Complementary documents

Fingrid publishes supplementary documents that apply alongside SJV2024. These cover modelling deliverables, cybersecurity requirements, and grid stability studies.

Key stakeholders

Fingrid (TSO)

Sets grid code specifications. Receives dynamic studies, reviews simulation models, and may attend commissioning tests for Type D systems.

Grid connection process

RNO (Relevant Network Operator)

The DSO or TSO at the connection point. Coordinates protection settings, approves test plans, and receives commissioning results. First point of contact for most compliance steps.

RO (Relevant Operator)

Designated by the asset owner to operate the BESS. Responsible for 24/7 availability, remote control interfaces, SCADA signals, and reporting status information to Fingrid.